The Cineramadome was a project that took some creative solutions to provide containment as well as safety while removing 55,000 s/f of spray applied sound proofing consisting of 90% Amosite.

The entire dome was scaffold decked to 75 feet top dead center and stepped down to a level of 55’ on the outer ring.

All of the work performed was staged, contained and performed atop of the deck.

Schedule: 3 weeks

Value: $200,000